Crane Lift Plan
And What Makes a Lift Critical
A lift plan is the lift worked out on paper before the crane picks: weights, radius, capacity, rigging, hazards and people.
Reviewed November 2026 against 29 CFR 1926.1432, 1926.751, 1926.1408.
What Goes in a Lift Plan
- ✓The load: weight from a reliable source, dimensions, center of gravity and pick points
- ✓Everything else on the hook: rigging, block, spreader bars, stowed jib and other deductions
- ✓The crane: model, boom length, counterweight, outrigger position, parts of line
- ✓The geometry: pick radius, set radius, boom angle and the quadrants the load swings through
- ✓Capacity: chart rating at the longest radius of the lift, and the percent of chart in use
- ✓The site: ground bearing and matting, power lines, underground hazards, obstructions, wind limits
- ✓The people: lift director, operator, rigger, signal person, and how they communicate
- ✓The sequence: each step of the lift and what stops it
Percent of Chart
Percent of chart = total lift weight ÷ chart capacity × 100.
If the load, rigging and block total 57,100 lb and the chart capacity at that radius and configuration is 66,500 lb, the lift is at 57,100 ÷ 66,500 = 86 percent of chart. That number is what reviewers look at first.
How to read the chart itself: crane load charts.
When a Plan Is Required, and What "Critical" Means
| Situation | What the rule says |
|---|---|
| More than one crane supporting the load | The operation must be planned by a qualified person, with engineering expertise if the qualified person says it is needed. A lift director reviews the plan with everyone involved (1926.1432) |
| Working near power lines | A planning meeting with the operator and crew to review the line location and the steps to prevent encroachment (1926.1408) |
| Hoisting personnel | A pre-lift meeting before the trial lift at each new location (1926.1431) |
| Steel erection critical lift | Defined as a lift over 75 percent of rated capacity, or one requiring more than one crane or derrick (1926.751) |
OSHA's crane rule, Subpart CC, does not define "critical lift". Site owners, contractors and agencies write their own definitions, and they commonly add personnel lifts, lifts over operating equipment, pick and carry, and anything a qualified person flags. Use the definition in force on your job.
5 Practice Questions: Crane lift plan
From the question bank in the app. Pick an answer, then open the explanation. For a scored test, try the NCCCO core practice test.
Operations
1. Which of the following is NOT listed as an example of a critical lift?
- AA routine lift at 40 percent of rated capacity over open ground
- BHoisting personnel
- CA pick-and-carry operation
- DA lift over process equipment
Show answer
Answer: A. A routine lift at 40 percent of rated capacity over open ground. Critical lifts include multi-crane lifts, lifts over 75 percent of capacity, personnel lifts, pick and carry, lifts over process equipment, and any lift a qualified person designates.
Operations
2. Before an operation in which more than one crane supports the load, the lift plan must be developed by…
- AA qualified person
- BThe most senior operator involved
- CThe crane rental company
- DOSHA's area office
Show answer
Answer: A. A qualified person. Multiple-crane lift plans must be developed by a qualified person and designed to meet the requirements of the subpart.
Load Charts
3. A lift plan sheet lists a chart capacity of 66,500 lb and a total lift weight of 57,100 lb. What percentage of chart is being used?
- AAbout 86%
- BAbout 66%
- CAbout 76%
- DAbout 92%
Show answer
Answer: A. About 86%. 57,100 / 66,500 = 0.859, so 86% of chart. That figure is the headline number on every lift plan sheet because it tells the reviewer instantly how little margin is left.
ASME B30.5 (Mobile Cranes)
4. According to ASME B30.5 Nonmandatory Appendix A, a critical lift plan shall be prepared:
- AOn all critical lifts prior to the commencement of those lifts
- BOnly for lifts over 100 tons
- CAfter the lift is completed, for records
- DOnly when OSHA requires it
Show answer
Answer: A. On all critical lifts prior to the commencement of those lifts. Appendix A-2 requires a critical lift plan, with documentation as determined by site supervision or project management, prepared on all critical lifts prior to commencement.
Rigging
5. Part of pre-lift planning is to confirm that...
- AThe load path and landing area are clear and no one is under the load
- BThe load exceeds 50 percent of capacity
- CThe tag line is removed
- DThe slings are lubricated
Show answer
Answer: A. The load path and landing area are clear and no one is under the load. The travel path and set-down area must be clear of people and obstructions, and personnel must stay out from under the suspended load.
Study the Whole Exam, Not 20 Questions
5,000+ practice questions across Core and every specialty, load chart trainers with the rating table on screen, timed exam simulations, and the pass guarantee.
Crane lift plan: Questions & Answers
Does OSHA require a lift plan for every crane lift?
What is a critical lift?
Who writes the lift plan?
How do you calculate percent of chart?
What weight goes in the plan?
This page is a study aid. It summarizes federal OSHA rules and industry standards and is not a substitute for the regulation, the manufacturer's manual or your employer's procedures. State plans and site rules can be stricter.