Tandem Lift
Multiple-Crane Lift Rules
A tandem lift uses two or more cranes on one load. Each crane can be overloaded by what the other one does.
Reviewed November 2026 against 29 CFR 1926.1432, 1926.1419.
What OSHA Requires
| Requirement | Detail |
|---|---|
| Plan | Developed by a qualified person before the operation begins, and designed to meet the requirements of the crane rule |
| Engineering | If the qualified person decides engineering expertise is needed, the employer must provide it |
| Lift director | A person who meets the criteria for both a competent person and a qualified person, or a competent person assisted by one or more qualified persons |
| Meeting | The lift director reviews the plan with all workers who will be involved |
| Signals | Where a signal person is in contact with more than one crane, there must be a system for identifying which crane each signal is for |
Sources: 29 CFR 1926.1432 and 1926.1419.
Why Tandem Lifts Go Wrong
Each crane carries a share of the load that depends on where its hook is relative to the load's center of gravity. If one crane hoists faster, swings or booms out of step, weight moves onto the other crane without warning.
Load lines that are not vertical side-load the booms, and booms are not built for side load.
- ✓Work out each crane's share from the pick points and center of gravity, then check each against its own chart
- ✓Leave margin. Many lift procedures hold each crane to 75 percent of chart or less on a tandem lift. That is a common policy figure, not an OSHA number
- ✓Keep load lines plumb throughout
- ✓Use one signal person where possible, and move one crane function at a time
- ✓Agree before the lift what stops it
Signals With More Than One Crane
The signal person has to make clear which crane a signal is for. OSHA gives two ways: identify the crane before giving the function and direction, or use an equally effective method.
Review the signals in our crane hand signals chart.
5 Practice Questions: Tandem lift
From the question bank in the app. Pick an answer, then open the explanation. For a scored test, try the NCCCO core practice test.
OSHA 1926 Subpart CC
1. According to OSHA 1926.1432, before beginning a lift in which more than one crane will support the load, the operation must be planned, and the plan must be developed by:
- AA qualified person
- BThe controlling entity
- CEach crane operator jointly
- DA registered professional engineer in every case
Show answer
Answer: A. A qualified person. 1926.1432(a) requires planning by a qualified person; if that person determines engineering expertise is needed, the employer must ensure it is provided.
OSHA 1926 Subpart CC
2. According to OSHA 1926.1432, a multiple-crane lift must be directed by:
- AA person meeting the criteria for both a competent person and a qualified person (or a competent person assisted by qualified persons)
- BThe senior crane operator
- CThe controlling entity's safety manager
- DAny signal person
Show answer
Answer: A. A person meeting the criteria for both a competent person and a qualified person (or a competent person assisted by qualified persons). 1926.1432(b)(1) requires the lift director to meet both competent and qualified person criteria (or be a competent person assisted by qualified persons), and (b)(2) requires the director to review the plan in a meeting with all workers involved.
Operations
3. During a multiple-crane lift, the load applied to each crane should not exceed what portion of that crane's capacity?
- A75 percent
- B50 percent
- C90 percent
- D100 percent, provided load lines stay vertical
Show answer
Answer: A. 75 percent. In multi-crane lifts, load lines must stay vertical and each crane should carry no more than 75 percent of its capacity, since side loading is the greatest failure risk.
Signals
4. A signal person directing more than one crane must, before giving each function and direction…
- AIdentify which crane the signal is for
- BGet verbal permission from every operator
- CSound an air horn twice
- DUse a different colored flag for each crane
Show answer
Answer: A. Identify which crane the signal is for. With multiple cranes, the signal person must identify the crane each signal is for before the function/direction, or use an equally effective identification method.
Operations
5. The qualified person decides that engineering expertise is needed to plan a multi-crane lift. The employer must…
- AEnsure that the engineering expertise is provided
- BSubstitute a second qualified person instead
- CReduce the load until engineering is unnecessary
- DProceed and document the concern
Show answer
Answer: A. Ensure that the engineering expertise is provided. Where the qualified person determines engineering expertise is needed for the plan, the employer must ensure it is provided.
Study the Whole Exam, Not 20 Questions
5,000+ practice questions across Core and every specialty, load chart trainers with the rating table on screen, timed exam simulations, and the pass guarantee.
Tandem lift: Questions & Answers
What is a tandem lift?
Who must plan a multiple-crane lift?
Who directs a tandem lift?
How much can each crane lift in a tandem lift?
Is a tandem lift a critical lift?
This page is a study aid. It summarizes federal OSHA rules and industry standards and is not a substitute for the regulation, the manufacturer's manual or your employer's procedures. State plans and site rules can be stricter.