OPERATIONS & LIFT PLANNING • CRANE EXAM TOPIC

Crane Man Basket
OSHA Personnel Platform Rules

Lifting people with a crane is allowed only when the usual ways of reaching the work are more dangerous or not possible. The rules are strict.

Reviewed November 2026 against 29 CFR 1926.1431.

Hoisting people in a crane man basket is prohibited unless conventional access such as a ladder, scaffold or aerial lift would be more hazardous or is not possible. When it is allowed, the total load must not exceed 50 percent of rated capacity, a trial lift is made before each shift, and the platform and rigging are proof tested to 125 percent of the platform's rated capacity at each jobsite.

The Main Rules

ItemRequirement
When it is allowedOnly when the employer shows conventional means of access would be more hazardous or are not possible
Crane capacityTotal load, including platform, people, hook, load line and rigging, no more than 50% of rated capacity for the radius and configuration
SetupUniformly level within 1% of level grade, on footing a qualified person has determined to be firm and stable
Platform strengthSupports its own weight plus at least 5 times the maximum intended load
Rigging and hooksAt least 5 times the maximum intended load. Hooks must be the type that closes and locks, and be closed and locked
Anti-two-blockA device that automatically prevents two-blocking
Trial liftUnoccupied platform loaded to at least the anticipated lift weight, immediately before each shift, and again when the crane is moved or the route changes
Proof test125% of the platform's rated capacity at each jobsite before hoisting people, and after any repair or modification
WindOver 20 mph at the platform, sustained or gusts, a qualified person must decide whether it is safe to lift
Fall protectionPersonal fall arrest attached to a structural member within the platform, except over water
Pre-lift meetingRequired before the trial lift at each new work location
TravelingHoisting people while the crane travels is prohibited, with narrow exceptions

Source: 29 CFR 1926.1431.

The Platform

  • ✓Designed by a qualified person familiar with structural design
  • ✓Guardrail system all the way around, enclosed from toeboard to mid-rail
  • ✓Grab rail inside the full perimeter
  • ✓Access gates that do not swing outward and have a device to keep them from opening by accident
  • ✓Enough headroom to stand upright
  • ✓Used only for people, their tools and the materials for the job, never as a material hoist

During the Lift

After the trial lift, a competent person inspects the crane, the ground and the platform. With people on board, the platform is lifted a few inches and checked for balance and security before going up.

Where the platform has no controls of its own, the operator stays at the crane controls, on site and in view of the equipment, the whole time the platform is occupied. Tag lines are used when needed to control the platform. If the weather turns, a qualified person decides whether to stop.

The anti-two-block rule is covered in two-blocking.

5 Practice Questions: Crane man basket

From the question bank in the app. Pick an answer, then open the explanation. For a scored test, try the NCCCO core practice test.

General Knowledge

1. A personnel platform and rigging shall be proof tested to what percent of the platform's rated capacity?

  1. A125%
  2. B100%
  3. C110%
  4. D200%
Show answer

Answer: A. 125%. Personnel platforms and rigging must be proof tested to 125% of the platform's rated capacity.

General Knowledge

2. According to OSHA 1926.1431, rigging hardware used in personnel platform applications must be able to support how many times the intended load?

  1. A5
  2. B3
  3. C3.5
  4. D7
Show answer

Answer: A. 5. OSHA 1926.1431 requires rigging for personnel platforms to support at least five times the maximum intended load.

Operations

3. What is the maximum wind speed for hoisting personnel unless a qualified person determines it is still safe?

  1. A20 mph
  2. B15 mph
  3. C25 mph
  4. D30 mph
Show answer

Answer: A. 20 mph. OSHA sets 20 mph (sustained or gusts) at the platform as the point where a qualified person must decide whether personnel lifting can proceed.

General Knowledge

4. A body harness system shall be attached to the personnel platform EXCEPT in what working situation?

  1. Aover water
  2. Bwhile welding
  3. Cless than 10 feet off the ground
  4. Dnear power lines
Show answer

Answer: A. over water. When working over water, tying off to the platform is not required because personal flotation requirements apply instead.

Operation Aids

5. Before hoisting personnel, the crane's anti-two block system must:

  1. Abe a prevention type that shuts down the functions causing two-blocking
  2. Bsound an audible alarm in the cab
  3. Cilluminate a warning light visible to the platform occupants
  4. Dbe tested monthly by a qualified person
Show answer

Answer: A. be a prevention type that shuts down the functions causing two-blocking. Correct: personnel hoisting requires an anti-two block PREVENTION device. The trap answers describe a WARNING system — a light or alarm alone does not satisfy the personnel-lifting requirement.

Study the Whole Exam, Not 20 Questions

5,000+ practice questions across Core and every specialty, load chart trainers with the rating table on screen, timed exam simulations, and the pass guarantee.

Crane man basket: Questions & Answers

Can you lift people with a crane?
Only when the employer can show that conventional access, such as a ladder, stairway, aerial lift, elevating work platform or scaffold, would be more hazardous or is not possible because of the structure or site conditions.
How much of the crane's capacity can a man basket use?
No more than 50 percent of the rated capacity for the radius and configuration, counting the platform, the people, tools, hook, load line and rigging.
What is a trial lift?
A lift of the empty platform, loaded with test weight to at least the anticipated lift weight, along the planned route to each location. It is done immediately before each shift in which people will be hoisted.
What is the proof test for a personnel platform?
125 percent of the platform's rated capacity, done at each jobsite before hoisting people and after any repair or modification. It can be done together with the trial lift.
What is the wind limit for a man basket?
When wind at the platform exceeds 20 mph, sustained or in gusts, a qualified person must determine whether it is safe to lift personnel. If it is not, the lift does not start or is stopped.

This page is a study aid. It summarizes federal OSHA rules and industry standards and is not a substitute for the regulation, the manufacturer's manual or your employer's procedures. State plans and site rules can be stricter.