Crane Man Basket
OSHA Personnel Platform Rules
Lifting people with a crane is allowed only when the usual ways of reaching the work are more dangerous or not possible. The rules are strict.
Reviewed November 2026 against 29 CFR 1926.1431.
The Main Rules
| Item | Requirement |
|---|---|
| When it is allowed | Only when the employer shows conventional means of access would be more hazardous or are not possible |
| Crane capacity | Total load, including platform, people, hook, load line and rigging, no more than 50% of rated capacity for the radius and configuration |
| Setup | Uniformly level within 1% of level grade, on footing a qualified person has determined to be firm and stable |
| Platform strength | Supports its own weight plus at least 5 times the maximum intended load |
| Rigging and hooks | At least 5 times the maximum intended load. Hooks must be the type that closes and locks, and be closed and locked |
| Anti-two-block | A device that automatically prevents two-blocking |
| Trial lift | Unoccupied platform loaded to at least the anticipated lift weight, immediately before each shift, and again when the crane is moved or the route changes |
| Proof test | 125% of the platform's rated capacity at each jobsite before hoisting people, and after any repair or modification |
| Wind | Over 20 mph at the platform, sustained or gusts, a qualified person must decide whether it is safe to lift |
| Fall protection | Personal fall arrest attached to a structural member within the platform, except over water |
| Pre-lift meeting | Required before the trial lift at each new work location |
| Traveling | Hoisting people while the crane travels is prohibited, with narrow exceptions |
Source: 29 CFR 1926.1431.
The Platform
- ✓Designed by a qualified person familiar with structural design
- ✓Guardrail system all the way around, enclosed from toeboard to mid-rail
- ✓Grab rail inside the full perimeter
- ✓Access gates that do not swing outward and have a device to keep them from opening by accident
- ✓Enough headroom to stand upright
- ✓Used only for people, their tools and the materials for the job, never as a material hoist
During the Lift
After the trial lift, a competent person inspects the crane, the ground and the platform. With people on board, the platform is lifted a few inches and checked for balance and security before going up.
Where the platform has no controls of its own, the operator stays at the crane controls, on site and in view of the equipment, the whole time the platform is occupied. Tag lines are used when needed to control the platform. If the weather turns, a qualified person decides whether to stop.
The anti-two-block rule is covered in two-blocking.
5 Practice Questions: Crane man basket
From the question bank in the app. Pick an answer, then open the explanation. For a scored test, try the NCCCO core practice test.
General Knowledge
1. A personnel platform and rigging shall be proof tested to what percent of the platform's rated capacity?
- A125%
- B100%
- C110%
- D200%
Show answer
Answer: A. 125%. Personnel platforms and rigging must be proof tested to 125% of the platform's rated capacity.
General Knowledge
2. According to OSHA 1926.1431, rigging hardware used in personnel platform applications must be able to support how many times the intended load?
- A5
- B3
- C3.5
- D7
Show answer
Answer: A. 5. OSHA 1926.1431 requires rigging for personnel platforms to support at least five times the maximum intended load.
Operations
3. What is the maximum wind speed for hoisting personnel unless a qualified person determines it is still safe?
- A20 mph
- B15 mph
- C25 mph
- D30 mph
Show answer
Answer: A. 20 mph. OSHA sets 20 mph (sustained or gusts) at the platform as the point where a qualified person must decide whether personnel lifting can proceed.
General Knowledge
4. A body harness system shall be attached to the personnel platform EXCEPT in what working situation?
- Aover water
- Bwhile welding
- Cless than 10 feet off the ground
- Dnear power lines
Show answer
Answer: A. over water. When working over water, tying off to the platform is not required because personal flotation requirements apply instead.
Operation Aids
5. Before hoisting personnel, the crane's anti-two block system must:
- Abe a prevention type that shuts down the functions causing two-blocking
- Bsound an audible alarm in the cab
- Cilluminate a warning light visible to the platform occupants
- Dbe tested monthly by a qualified person
Show answer
Answer: A. be a prevention type that shuts down the functions causing two-blocking. Correct: personnel hoisting requires an anti-two block PREVENTION device. The trap answers describe a WARNING system — a light or alarm alone does not satisfy the personnel-lifting requirement.
Study the Whole Exam, Not 20 Questions
5,000+ practice questions across Core and every specialty, load chart trainers with the rating table on screen, timed exam simulations, and the pass guarantee.
Crane man basket: Questions & Answers
Can you lift people with a crane?
How much of the crane's capacity can a man basket use?
What is a trial lift?
What is the proof test for a personnel platform?
What is the wind limit for a man basket?