Load Moment Indicator (LMI)
What It Does and What OSHA Requires
The LMI is the computer that compares what the crane is doing to its load chart. It helps the operator; it does not replace the chart.
Reviewed November 2026 against 29 CFR 1926.1416, 1926.1401, 1926.1417.
Indicator vs Limiter vs Load Weighing Device
| Device | What it does |
|---|---|
| Load weighing device | Shows the weight on the hook. The operator still has to compare it to the chart |
| Load moment (rated capacity) indicator | Senses load and radius, compares to rated capacity, shows percent of capacity and warns as the limit approaches |
| Load moment (rated capacity) limiter | Does the same, then cuts power to functions that increase the loading: hoisting up, telescoping out, luffing out. Functions that reduce loading keep working |
Definitions: 29 CFR 1926.1401.
What OSHA Requires
- ✓Equipment other than derricks and articulating cranes, manufactured after March 29, 2003 with a rated capacity over 6,000 pounds, must have at least one: load weighing device, load moment indicator, or load moment limiter
- ✓It is a Category II operational aid. If it stops working it must be repaired within 30 calendar days. If parts were ordered within 7 days and arrive late, the repair is due within 7 days of receiving them
- ✓Operations must not begin unless listed operational aids work, or the temporary alternative measures are in place
- ✓If it fails during a lift, the operator safely stops until the alternative measures are in place or the device works again
- ✓Temporary alternative: the load weight is determined from a source recognized by the industry, or by a recognized calculation method, and given to the operator before the lift
What the LMI Cannot Do
An LMI only knows what it has been told. If the wrong configuration is entered, such as the wrong counterweight, outrigger position, parts of line or boom mode, its numbers are wrong and so are its warnings.
It also reacts to what is happening now. It will not warn you that the ground is soft, that the load is about to swing out, or that the wind is rising. Plan the lift from the load chart first and treat the LMI as a check.
OSHA also allows the LMI to be used to verify load weight: begin hoisting, and if the reading shows the load is over 75 percent of rated capacity at the longest radius of the lift, stop until the weight is confirmed from a reliable source.
5 Practice Questions: Load moment indicator (LMI)
From the question bank in the app. Pick an answer, then open the explanation. For a scored test, try the NCCCO core practice test.
General Knowledge
1. One purpose of a load moment indicator is to:
- Awarn the operator of an overload condition
- Blimit the amount of swingout of the load
- Cindicate the amount of boom deflection
- Dmonitor the amount of wind effect on the load
Show answer
Answer: A. warn the operator of an overload condition. A load moment indicator warns the operator when the crane approaches or reaches an overload condition.
Operation Aids
2. A rated capacity LIMITER (RCL) differs from a rated capacity INDICATOR (RCI) because the limiter…
- AAutomatically stops the function that would exceed capacity
- BOnly sounds an alarm
- COnly lights a display
- DOnly records the lift for later review
Show answer
Answer: A. Automatically stops the function that would exceed capacity. An indicator warns; a limiter actually stops the aggravating motion — the same warn-versus-prevent logic as the anti-two-block device.
Operation Aids
3. The load moment that an LMI monitors is the product of the load weight and…
- AThe horizontal radius from the tipping axis
- BThe vertical hoisting height
- CThe boom's own weight
- DThe number of parts of line
Show answer
Answer: A. The horizontal radius from the tipping axis. Load moment equals load weight multiplied by the horizontal radius; the LMI tracks this against rated capacity.
Operation Aids
4. Cranes manufactured after March 29, 2003 must have a load weighing device, load moment indicator, or load moment limiter when the rated capacity exceeds what?
- A6,000 pounds
- B10,000 pounds
- C15,000 pounds
- D26,000 pounds
Show answer
Answer: A. 6,000 pounds. Equipment made after March 29, 2003 with a rated capacity over 6,000 pounds must have at least one load weighing device, LMI, or load moment limiter.
Operation Aids
5. If the LMI malfunctions mid-job, the operator should…
- AStop until temporary alternative measures are in place
- BTurn it off and continue carefully
- CEstimate loads by math and keep going
- DFix it personally
Show answer
Answer: A. Stop until temporary alternative measures are in place. Operations cease until the aid is repaired or approved alternatives are set up.
Study the Whole Exam, Not 20 Questions
5,000+ practice questions across Core and every specialty, load chart trainers with the rating table on screen, timed exam simulations, and the pass guarantee.
Load moment indicator (LMI): Questions & Answers
What does LMI stand for on a crane?
What is load moment?
Is an LMI required on every crane?
Can you operate a crane with a broken LMI?
Can the operator override the LMI?
This page is a study aid. It summarizes federal OSHA rules and industry standards and is not a substitute for the regulation, the manufacturer's manual or your employer's procedures. State plans and site rules can be stricter.