OPERATIONS & LIFT PLANNING • CRANE EXAM TOPIC

Parts of Line
How to Work Out What You Need

Parts of line is the number of rope lines holding up the hook block. It sets how much the hoist can lift and how fast.

Reviewed November 2026 against 29 CFR 1926.1417(o), 1926.1414.

Parts of line is the number of lines of hoist rope supporting the load block. To find the minimum, divide the gross load by the allowable line pull for one part and round up. A 36,500 lb gross load on a hoist with 8,000 lb of line pull needs 36,500 ÷ 8,000 = 4.56, so 5 parts. More parts lift more but hoist slower.

The Calculation

Minimum parts of line = gross load ÷ allowable line pull per part, rounded up.

The gross load is everything hanging from the boom tip: the load, the rigging, the hook block and, on long lines, the rope itself. The allowable line pull comes from the crane's hoist and rope data, usually printed with the load chart.

Always round up. 4.1 parts means 5.

Then check the answer against the load chart. Adding parts of line never raises the chart rating. The lowest of the chart capacity, the hoist line capacity and the block capacity is what you can lift.

What Changes When You Add Parts

More parts of lineEffect
Line capacityGoes up roughly in proportion to the number of parts
Hook speedGoes down in proportion. Two parts is about half the speed of one
Rope on the drumMore rope is used for the same hook travel
Block weightBigger blocks weigh more and must be deducted from capacity
FrictionEach sheave adds a little loss, so the gain is slightly less than the simple math

Related Points That Show Up on Exams

  • ✓Available line pull drops as rope builds on the drum. Each layer increases the effective drum diameter
  • ✓Reeve the block evenly. An unbalanced block tilts and wears the rope and sheaves
  • ✓The LMI must be set to the parts of line actually reeved, or its limits are wrong
  • ✓Keep at least two full wraps on the drum at all times. OSHA requires it on the load and boom hoist drums
  • ✓Rotation-resistant rope has stricter rules for use and inspection. See wire rope inspection

5 Practice Questions: Parts of line

From the question bank in the app. Pick an answer, then open the explanation. For a scored test, try the NCCCO core practice test.

Definitions

1. What is 'available line pull'?

  1. AThe pulling force applied by the hoist drum
  2. BMinimum breaking strength divided by the design factor
  3. CThe rope's catalog breaking strength
  4. DThe tension carried by each part of line
Show answer

Answer: A. The pulling force applied by the hoist drum. Available line pull is the pulling force the hoist drum applies, and it drops as more layers of rope build up on the drum.

General Knowledge

2. An operator plans to pick a gross load that weighs 36,500 pounds and the crane's line pull is 8,000 lbs. What are the minimum parts of line required?

  1. A5
  2. B4
  3. C6
  4. D7
Show answer

Answer: A. 5. 36,500 lb divided by 8,000 lb per line is 4.56, which must be rounded up to 5 parts of line.

General Knowledge

3. As rope spools onto the hoist drum and the layers increase, available line pull:

  1. Adecreases
  2. Bdepends on the load
  3. Cincreases
  4. Dremains constant
Show answer

Answer: A. decreases. Each added layer increases the effective drum diameter, reducing the available line pull.

Technical Knowledge

4. Adding parts of line in the reeving affects lifting capacity so that available capacity roughly…

  1. AMultiplies with the number of parts, up to the rope and drum limits
  2. BHalves with each part added
  3. CIs unaffected by parts of line
  4. DDepends only on boom angle
Show answer

Answer: A. Multiplies with the number of parts, up to the rope and drum limits. More parts of line multiply the liftable weight because each part carries a share, limited by rope strength and drum line pull. Trap: added parts still cannot exceed the chart rating.

Technical Knowledge

5. Doubling a hoist reeving from one part of line to two parts:

  1. Aroughly doubles capacity while cutting line speed about in half
  2. Bdoubles both capacity and line speed
  3. Cincreases speed but halves capacity
  4. Dchanges only speed, not capacity
Show answer

Answer: A. roughly doubles capacity while cutting line speed about in half. Added parts of line share the load and raise capacity, but hoisting speed drops proportionally; the speed-gain option reverses the physics.

Study the Whole Exam, Not 20 Questions

5,000+ practice questions across Core and every specialty, load chart trainers with the rating table on screen, timed exam simulations, and the pass guarantee.

Parts of line: Questions & Answers

What does parts of line mean?
The number of lines of hoist rope running between the boom tip sheaves and the load block that share the weight of the load.
How do you calculate parts of line?
Divide the gross load by the allowable line pull of a single part and round up to the next whole number.
Does adding parts of line increase crane capacity?
It increases what the hoist line can carry, up to the load chart rating. It never lets you lift more than the chart allows.
Why is the hoist slower with more parts?
The drum has to take in more rope for each foot the hook rises. With four parts, the drum reels in four feet of rope to raise the hook one foot.
Is the hook block part of the load?
Yes. The block, the rigging and everything else below the boom tip is deducted from the chart capacity to get what you can actually pick.

This page is a study aid. It summarizes federal OSHA rules and industry standards and is not a substitute for the regulation, the manufacturer's manual or your employer's procedures. State plans and site rules can be stricter.