What the Each-Shift Inspection Covers
A competent person looks for apparent deficiencies in at least these items:
- ✓Control mechanisms, for maladjustments that interfere with proper operation
- ✓Control and drive mechanisms, for excessive wear and contamination by lubricants, water or other foreign matter
- ✓Air, hydraulic and other pressurized lines, for deterioration or leaks
- ✓Hydraulic system fluid level
- ✓Hooks and latches, for deformation, cracks, excessive wear or damage
- ✓Wire rope reeving and the wire rope itself
- ✓Electrical apparatus, for malfunction, deterioration, dirt or moisture
- ✓Tires, when in use, for inflation and condition
- ✓Ground conditions around the crane, including under and around outriggers and stabilizers
- ✓Level position, before each shift and after each move and setup
- ✓Operator cab windows, for cracks or other damage that would block the view
- ✓Rails, rail stops and rail clamps on rail-mounted equipment
- ✓Safety devices and operational aids, for proper operation
Inspection Schedule and Records
| Inspection | By | Record kept |
|---|---|---|
| Each shift | Competent person | No written record required |
| Monthly | Competent person | 3 months minimum |
| Annual / comprehensive | Qualified person | 12 months minimum |
| Post-assembly, repair, modification, severe service | Qualified person | Not specified |
| Idle 3 months or more | Qualified person | As for monthly |
Source: 29 CFR 1926.1412. The monthly record lists the items checked, the results, the inspector's name and signature, and the date.
What Is Different About the Annual Inspection
The annual inspection covers everything in the shift inspection, then goes further: structural members, bolts and rivets, welds, sheaves and drums, brake and clutch parts, safety devices, power plants, chains and sprockets, travel components, hydraulic pumps, motors, valves, hoses and cylinders, outrigger pads and more. Disassembly is required as needed to finish it, and it includes functional testing.
If the qualified person finds a safety hazard, the crane comes out of service until it is corrected. If the item is not yet a hazard but needs watching, it gets checked in the monthly inspections.
Who does which inspection is laid out in who should inspect a crane. Wire rope has its own section: wire rope inspection.
5 Practice Questions: OSHA crane inspection requirements
From the question bank in the app. Pick an answer, then open the explanation. For a scored test, try the NCCCO core practice test.
General Knowledge
1. According to OSHA 1926.1412, which of the following is part of a crane shift inspection?
- Aall of the above (control mechanisms, ground conditions, hydraulic hoses)
- Bcontrol mechanisms only
- Cground conditions only
- Dhydraulic hoses only
Show answer
Answer: A. all of the above (control mechanisms, ground conditions, hydraulic hoses). OSHA 1926.1412 shift inspections include control mechanisms, ground conditions, hydraulic hoses, and more.
General Knowledge
2. According to OSHA 1926.1412, a monthly inspection includes:
- Aa documented shift inspection
- Ban annual inspection
- Ca comprehensive inspection
- Da post assembly inspection
Show answer
Answer: A. a documented shift inspection. The OSHA monthly inspection is essentially a shift inspection that must be documented and retained.
Inspections
3. OSHA monthly inspection documents must be retained for a minimum of how long?
- A3 months
- B12 months
- C1 month
- D5 years
Show answer
Answer: A. 3 months. Monthly inspection records are kept at least three months, while annual inspection records are kept at least twelve months.
Inspections
4. Annual/comprehensive inspection documents must be retained for a minimum of…
- A12 months, by the employer that conducts the inspection
- B3 months
- C5 years
- DThe life of the crane
Show answer
Answer: A. 12 months, by the employer that conducts the inspection. Annual inspection documentation is kept at least 12 months by the employer that conducted it; monthly records are kept 3 months.
Inspections
5. A crane is classified as 'equipment not in regular use,' requiring a qualified person's inspection before service, after being idle how long?
- A3 months or more
- B1 month or more
- C6 months or more
- D12 months or more
Show answer
Answer: A. 3 months or more. A crane idle for three months or more must be inspected by a qualified person before returning to service.
Study the Whole Exam, Not 20 Questions
5,000+ practice questions across Core and every specialty, load chart trainers with the rating table on screen, timed exam simulations, and the pass guarantee.
OSHA crane inspection requirements: Questions & Answers
How often does OSHA require a crane to be inspected?
Does the daily crane inspection have to be documented?
How long do crane inspection records have to be kept?
What happens if a crane has been sitting unused?
Which OSHA standard covers overhead crane inspections?
This page is a study aid. It summarizes federal OSHA rules and industry standards and is not a substitute for the regulation, the manufacturer's manual or your employer's procedures. State plans and site rules can be stricter.