INSPECTIONS & STANDARDS • CRANE EXAM TOPIC

Who Should Inspect a Crane?
The Person OSHA Names for Each Inspection

OSHA names a specific kind of person for every crane inspection, and the written exams ask which is which.

Reviewed November 2026 against 29 CFR 1926.1412, 1926.1413, 1926.1401.

On construction cranes, a competent person does the visual inspection before or during each shift and the monthly inspection. A qualified person does the annual (comprehensive) inspection, and also inspects after assembly, after safety-related repairs or modifications, after severe service, and after the crane has sat idle three months or more.

Who Does Each Crane Inspection

InspectionWhoWhenRecord OSHA requires
Each shift (pre-shift)Competent personStarted before the shift, finished before or during itNone
MonthlyCompetent personEvery month the crane is in serviceItems checked, results, name, signature and date. Kept 3 months
Annual / comprehensiveQualified personAt least every 12 monthsKept 12 months
Post-assemblyQualified personWhen assembly is finished, before useNot specified
After a safety-related repair or adjustmentQualified personBefore the crane is used againNot specified
After a modification or additionQualified personBefore the crane is used againNot specified
Severe service (overload, shock load, corrosive exposure)Qualified personUse stops until the inspection is doneNot specified
Idle 3 months or moreQualified personBefore the crane goes back to workSame as monthly
Wire rope, each shiftCompetent personBefore or during each shiftNone

Source: 29 CFR 1926.1412 and 1926.1413. These are the rules for cranes used in construction.

Competent Person vs Qualified Person

A competent person can spot existing and predictable hazards and has the authority to correct them right away. Often that is the operator, as long as the operator meets both halves of the definition.

A qualified person has a recognized degree, certificate or professional standing, or extensive knowledge, training and experience, and has shown they can solve problems in that subject. The annual inspection needs that deeper knowledge because it can call for taking components apart.

Full comparison: competent person vs qualified person.

What Happens When the Inspection Finds Something

On a shift inspection, the competent person decides on the spot whether the deficiency is a safety hazard. If it is, the crane comes out of service until it is corrected. If a safety device is not working, the crane does not run until it is fixed.

The shift inspection is visual. OSHA says taking components apart and booming down are not required unless what the inspector sees calls for a closer look.

5 Practice Questions: Who inspects a crane

From the question bank in the app. Pick an answer, then open the explanation. For a scored test, try the NCCCO core practice test.

General Knowledge

1. According to OSHA 1926.1412, who is responsible for conducting the inspections prior to or during each shift?

  1. Acompetent person
  2. Bdesignated person
  3. Cassigned person
  4. Dqualified person
Show answer

Answer: A. competent person. OSHA 1926.1412 requires a competent person to conduct shift inspections.

Inspections

2. The pre-shift visual inspection must be performed by a…

  1. ACompetent person
  2. BQualified engineer
  3. CDesignated manager
  4. DCertified rigger
Show answer

Answer: A. Competent person. OSHA assigns shift visual inspections to a competent person.

Inspections

3. The annual/comprehensive crane inspection must be performed by which person?

  1. AA qualified person
  2. BA competent person
  3. CAn appointed person
  4. DA designated signal person
Show answer

Answer: A. A qualified person. Each-shift and monthly inspections require a competent person, but the annual/comprehensive inspection must be done by a qualified person.

Inspections

4. Under OSHA 1926.1412, the monthly visual crane inspection must be performed by a…

  1. ACompetent person
  2. BQualified person
  3. CCertified operator only
  4. DRegistered professional engineer
Show answer

Answer: A. Competent person. Shift and monthly visual inspections require a competent person; the annual inspection requires a qualified person.

Wire Rope

5. Each-shift visual wire rope inspections are the responsibility of a:

  1. ACompetent person
  2. BQualified engineer only
  3. CThe equipment manufacturer
  4. DAny available laborer
Show answer

Answer: A. Competent person. OSHA assigns the each-shift wire rope inspection to a competent person who can identify existing and predictable hazards.

Study the Whole Exam, Not 20 Questions

5,000+ practice questions across Core and every specialty, load chart trainers with the rating table on screen, timed exam simulations, and the pass guarantee.

Who inspects a crane: Questions & Answers

Who should do the pre-shift inspection of a crane?
A competent person. OSHA 1926.1412(d) requires a competent person to begin a visual inspection before each shift the crane will be used and finish it before or during that shift.
Can the crane operator do the daily inspection?
Yes, if the operator meets the definition of a competent person: able to identify existing and predictable hazards and authorized to take prompt corrective action.
Who does the annual crane inspection?
A qualified person, at least every 12 months. The record has to be kept for at least 12 months by the employer that did the inspection.
Does OSHA require a third-party crane inspector?
The federal rule asks for a qualified person, not a third party. Some states, cities and project owners add their own third-party requirement, so check the rules where you work.
Is it the same for overhead cranes in a shop?
No. Overhead and gantry cranes in general industry fall under 29 CFR 1910.179, which sets frequent inspections (daily to monthly) and periodic inspections (every 1 to 12 months).

This page is a study aid. It summarizes federal OSHA rules and industry standards and is not a substitute for the regulation, the manufacturer's manual or your employer's procedures. State plans and site rules can be stricter.