PEOPLE & ROLES • CRANE EXAM TOPIC

Assembly/Disassembly Director
Who the A/D Director Is and What They Do

Putting a crane together and taking it apart is some of the most hazardous work around it. OSHA puts one person in charge.

Reviewed November 2026 against 29 CFR 1926.1404, 1926.1401.

The A/D director is the person who oversees and directs all crane assembly and disassembly. OSHA requires that person to meet the criteria for both a competent person and a qualified person, or to be a competent person assisted by one or more qualified persons. If one person does the assembly alone, that person must be both.

What the A/D Director Must Do

  • ✓Understand the procedures. The manufacturer's, or the employer's where those are allowed
  • ✓Review them right before starting, unless the director already understands them and has used them on the same type and configuration of crane
  • ✓Brief the crew. Before work starts, make sure each crew member understands their tasks, the hazards of those tasks, and the positions and locations to stay out of
  • ✓Brief again when someone takes on a different task or a new person joins
  • ✓Protect people out of view. Before going where the operator cannot see them, in, on or under the crane, a crew member tells the operator. The operator does not move anything until told the person is clear
  • ✓Confirm the ground. If ground conditions are not adequate, the director's employer takes it up with the controlling entity

The 12 Hazards the A/D Director Has to Address

HazardWhat it means
Site and ground bearing conditionsAdequate for assembly and for supporting the crane during it
Blocking materialRight size, amount, condition and stacking to hold the loads
Proper location of blockingPlaced to protect the structure and support stability
Verifying assist crane loadsThe assist crane's load is worked out before the pick
Boom and jib pick pointsChosen to prevent structural damage and keep the lift balanced
Center of gravityIdentified where needed for stability, or handled with extra precautions if it cannot be
Stability upon pin removalBoom sections, suspensions and components blocked or rigged before pins come out
SnaggingSuspension ropes and pendants kept from catching on pins, bolts and keepers
Struck by counterweightsCounterweights properly supported and hoisted
Boom hoist brake failureBrake tested, or boom otherwise secured, before relying on it
Loss of backward stabilityChecked before swinging the upper, traveling, and attaching or removing components
Wind speed and weatherEffects accounted for before and during the work

Source: 29 CFR 1926.1404(h).

Related Rules During Assembly

Rigging work during assembly and disassembly must be done by a qualified rigger. Synthetic slings must be protected from sharp edges and used to the manufacturer's instructions.

Nobody is under the boom, jib or other components while pins are being removed, unless the employer shows that site constraints require it and follows written procedures to limit the risk.

When assembly is finished, a qualified person inspects the crane to confirm it is configured to the manufacturer's criteria before it is used. See who inspects a crane.

5 Practice Questions: Assembly/disassembly (A/D) director

From the question bank in the app. Pick an answer, then open the explanation. For a scored test, try the lattice boom practice test.

Site Setup

1. To direct an assembly/disassembly operation alone, the A/D director must meet the criteria for:

  1. ABoth a competent person and a qualified person
  2. BA qualified person only
  3. CA competent person only
  4. DA certified lift director
Show answer

Answer: A. Both a competent person and a qualified person. Assembly/disassembly must be directed by someone meeting both competent and qualified person criteria, or a competent person assisted by qualified persons.

Site Setup

2. Before assembly begins, what information about each crane component must be readily available?

  1. AIts weight
  2. BIts purchase date
  3. CIts country of manufacture
  4. DIts paint specification
Show answer

Answer: A. Its weight. The weight of each component must be readily available during assembly/disassembly.

Rigging

3. During crane assembly, rigging work must be done by…

  1. AA qualified rigger
  2. BThe operator
  3. CThe safety manager
  4. DAny crew member
Show answer

Answer: A. A qualified rigger. OSHA requires a qualified rigger for rigging during assembly and disassembly.

General Knowledge

4. Booms that are being assembled or disassembled on the ground with or without support of the boom harness should be:

  1. ASecurely blocked to prevent dropping of the boom and/or boom sections
  2. BPinned at connection points with hardened boom pins
  3. CAttached at connecting points with nylon slings
  4. DAssembled with the longest boom section first
Show answer

Answer: A. Securely blocked to prevent dropping of the boom and/or boom sections. Boom sections must be securely blocked during assembly/disassembly so the boom cannot drop when pins are removed.

Site Setup

5. During assembly and disassembly, the manufacturer may require what counterweight change?

  1. AMore counterweight than the normal operating maximum
  2. BRemoval of all counterweight
  3. CExactly half the operating counterweight
  4. DMoving counterweight to the front of the carrier
Show answer

Answer: A. More counterweight than the normal operating maximum. Excessive counterweight — beyond the operating maximum — may be required by the manufacturer during assembly and disassembly.

Study the Whole Exam, Not 20 Questions

5,000+ practice questions across Core and every specialty, load chart trainers with the rating table on screen, timed exam simulations, and the pass guarantee.

Assembly/disassembly (A/D) director: Questions & Answers

Who oversees and directs all crane assembly and disassembly operations?
The assembly/disassembly director, called the A/D director in OSHA 1926.1404.
What qualifications does an A/D director need?
The person must meet the criteria for both a competent person and a qualified person, or be a competent person assisted by one or more qualified persons. OSHA does not require a specific card for the role.
Is the A/D director the same as the lift director?
No. The A/D director is in charge of putting the crane together and taking it apart. The lift director is in charge of a lift. One person can be both if they meet the criteria for each.
Can the crane operator be the A/D director?
Yes, if the operator meets the competent person and qualified person criteria for the assembly work, or is a competent person assisted by qualified persons.
Does the A/D director have to follow the manufacturer's procedures?
Assembly and disassembly must follow the manufacturer's procedures, or employer procedures that meet OSHA 1926.1406. The A/D director must understand whichever is used.

This page is a study aid. It summarizes federal OSHA rules and industry standards and is not a substitute for the regulation, the manufacturer's manual or your employer's procedures. State plans and site rules can be stricter.